- Installation
Installation of the systems pend48 & pend
The installation of the tracks is initially the same for the LightLight and Sense System. However, please note the instructions when connecting the Buschfeld light track. On this How it Works page, the installation of the systems is explained in short steps.
Full assembly instructions can be found here >>
Fix the cable suspension system on the ceiling, spacing between the cables 2000 mm maximum. Cable suspension 250 mm max. from the end of the track.
Bring all wire rope holders to the desired height, align them with a laser spirit level. Secure heavy control gear such as Cube, Bigbox and Bigbox48 (at track level) with an additional rope suspension. Insert the wire rope holder into the upper rail channel and screw in place.
Align the tracks with a spirit level and readjust the rope lengths on the wire rope holder if necessary. Place protruding rope ends in the upper rail channel or cut to length.
power feeds with power rods
Installation to be carried out by qualified personnale only! Disconnect the system!
Lighting tracks Sense System or LightLight:
When connecting the power feed and the control gear, the + / - polarity must be observed!
+ Brass inner conductor of the track
- track itself
The polarity is usually also marked with a sticker on the power feed.
Shorten the feeder rods
1st Length L2 = upper edge of track to the round end of the plug, L1 + 5 mm (tolerance +0/-1 mm)
2nd trim carefully (taper) so as not to damage the contact inter- faces in the connectors
3rd connect the feeder rod and the plug by pushing the coupling bushing upwards
power feed for cable
Installation to be carried out by qualified personnale only! Disconnect the system!
Lighting tracks Sense System or LightLight:
When connecting the power feed and the control gear, the + / - polarity must be observed!
+ Brass inner conductor of the track
- track itself
The polarity is usually also marked with a sticker on the power feed.
Use only stranded cables with wire end sleeves in the screw contacts of the pendant track. No rigid lines! Please note the marking (+) for the connection of the live conductor.
Installation of the control gear for visual mounting
Installation to be carried out by qualified personnale only! Disconnect the system!
Secure heavy control gear (A) such as Cube, Bigbox and Bigbox48 in the designer housing (on track level) for visible mounting with an additional cable suspension (D). Insert the cord holder into the upper track channel and screw in place.
Remove the design housing carefully from the base plate, turn the locking bolts (E) on the side of the adapter to 90°. One adapter has a golden contact pin (B), this adapter must be in contact with the inner conductor of the track. If necessary, turn the base plate by 180 °.
Insert both adapters into the rail channel, pressing firmly into the track; turn back the side latches (E) of the adapter by 90 °. Establish a connection on the primary side. With Bigbox, plug the earth cable onto the earth lug on the housing cover.
Carefully put on the housing cover, to do this, gently press all springs together and slide the housing (G) on.